| 2000
- 2002 |
Field Operations Coordinator with
BMH Americas Inc., California
Reporting to: Operations
| Responsibilities
and Assignments |
|
|
- Finalizing
installation of gypsum Board
Manufacturing plant in Kedaung,
Indonesia
- Finalized
installation and start up of
Cement transfer system,
Redwood City, California.
- Installation of CP
Mills: EM-47, EM-59 and High Burn
for BPB.,
Termoly, Italy.
- Distributed bid
packages, negotiated contracts,
and responsible
for follow up on equipment
fabrication and installation.
- Participated in
commissioning.
|
|
1998
-
2000 |
Field Operations Coordinator with
AKI Dryer Manufacturers, USA
Reporting to: Operations
| Responsibilities
and Assignments |
|
|
- Construction of
Gypsum Board Manufacturing
Dryers, in Stawiany, Poland
and Melnik, Czech Republic
- Project Management
and start up's
|
|
| 1998 |
Mechanical Consultant with
BPB British Gypsum
Reporting to: Operations
| Responsibilities
and Assignments |
|
|
Seconded
to BPB Placo do Brasil Ltda, Mogi das
Cruzes, Brazil
- Gypsum Board
Manufacturing Factory.
- Responsible for
the installation of the board
line equipment,
quality control,
- checking
designs, progress of
contractual claims,
- prepare documents
for commissioning and operation.
|
|
1997
- 1998
|
Mechanical Manager with
Thai Gypsum Products, Thailand
Reporting to: Project Manager Operations
| Responsibilities
and Assignments |
|
|
Seconded
to Shanghai Orient Gypsum Co. Ltd
- Gypsum Board
Manufacturing Factory.
- Responsible for
the fabrication and installation
of associated equipment.
- Checking drawings
and designs, assembling and
evaluating bid packages.
- Monitoring
progress of work and schedule.
- Quality control,
checking and approving progress
claims
- Approving scope
changes and checking contractual
claims.
Seconded to Thai Gypsum
Suria Indonesia, Cikampek Indonesia
- Gypsum Board
Manufacturing Plant.
- Responsible for
the installation of all
mechanical and piping related
works,
- Checking designs,
awarding of mechanical contracts,
- Fabrication of
equipment , checking progress and
contractual claims
- Day to day
supervision of the contractors.
|
|
| 1987
- 1996 |
Construction Superintendent with
United States Gypsum, USA
Reporting to: Project Manager Operations
| Responsibilities
and Assignments |
|
|
Seconded
to USG Interiors, Greenville Mississippi
- Construction of
Ceiling Tile No. 3 line
- Assistant Owner
Representative.
- Responsible for
mechanical and piping related
works.
- Coordinated the
contracts, labor and material
requirements.
Seconded to USG Co Plaster
City California
- Construction of
No. 2 Board Line
- Responsible with,
mechanical and piping
installation as well
Civil and electrical contractual
works falling within the scope of
owner representatives
responsibility.
Seconded as Mechanical
Consultant to Thai Gypsum
Products, Leam Chabang, Thailand
- Construction of a
new Board Line in Leam Chabang,
- Responsible for
equipment installation and local
fabrication.
- Supervised and
assisted in the setting, assembly
and alignment of all equipment.
- Involved in
training Thai staff for operation
and maintenance.
Seconded as Mechanical Inspection
Supervisor to USG Interiors
Aubange Belgium
- Construction of
new Ceiling Tile Manufacturing
Factory
- Assisted in the
supervision of installation of
the Ceiling Tile plant.
- Preparation of
weekly progress reports
- monitoring the
contractors quality
assurance and quality control
procedures.
Seconded as Mechanical
Supervisor to USG Interiors
Cloquet Minnesota
- Equipment
installation, supervision of the
contractors.
|
|
1984
-
1987 |
Precision Millwright with
Daniel Construction Co, USA
Reporting to: Field Operations
| Responsibilities
and Assignments |
|
|
Seconded
to Carolina Power and Light - Sharon
Harries Nuclear Power Plant
Apex North Carolina - USA
- Worked on final
motor alignment in the
Containment,
Reactor Accelerating and Fuel
Handling Building.
- Monitored the pipe
displacement under welding
stress.
|
|
1978
-
1983 |
Tool and Die Maker and Supervisor with
Electro Mechanica Turda Romania
Reporting to: Manufacturing Operations
| Responsibilities
and Assignments |
|
|
Porcelain
Insulator Manufacturing Company,
- Fabricating,
assembling and testing molds for
manufacturing insulators.
- As Supervisor,
responsible for purchasing,
fabricating and testing
replacement molds.
- Coordinate
purchasing, labor, material